53A, 53B and 53C Sylvan Crescent
Main contractor and project manager for consent management, demolition and decontamination.
Outline of Work
-
Resource Consent (sub-division and land-use) for residential subdivision and development. The Resource Consent consisted of:
-
A new vehicle crossing
-
Public Stormwater Extension
-
Sanitary Sewer public line bridging.
-
-
Project Management
-
Engineering approval for public drainage works
-
Building consent included:
-
2 x double level brick and weatherboard dwellings
-
Double internal garage per dwelling
-
4 x double bedrooms per dwelling
-
1 x living area per dwelling
-
3 x toilet and bathrooms per dwelling
-
Relocation of 1 x single level house onsite with new foundations and piles
-
Timeline
Total Duration: 9 months
Project commenced in late 2017 and was completed successfully in mid 2018.